Project: Flow Metering and Data Collection will be used to initiate and perform the preliminary work associated with a drainage study and future sewer separation projects. Activities will include video inspection and sewer flow metering. These activities will take place intermittently over the next few months. Sewer flow metering devices will be installed throughout the project area and monitored periodically.
Contractors: CDM Smith, Hart Consults
Schedule: April to November
Project Outreach Construction Notices:
Construction Notice August
Construction Notice April
Project Area Map