Integrated Plan Implementation Consent Order 2026 Q2 Public Meeting September 10, 2026 6:00 PM
Project: Work includes construction of new storm drains, storm drain stub connections, and replacement water mains on portions of Manchester Street, Branford Street, Granby Street and Lyme Street. Replacement water mains will also be constructed on portions of Lyme Street, Palm Street, and Westminster Street. Private Property work is also being offered including sewer back up prevention (back water check valves, sump pumps) and sewer inflow separation (gutters, yard drains, etc.)
Number of Properties: 190
Schedule: Construction begins Spring 2027 with final restoration projected for 2029
Cost: $19.5 million
Project Outreach Construction NoticesSurvey flyer(attached)