The West Branch Reservoir / Goodwin Dam in Hartland is closed due to high water levels.
Woodstock and Branford Sewer Separation Project Area MapProject: Work includes installation of storm drain stub connections, sewer main lining and sewer house connection lining and manhole lining. Private Property work is also being offered including sewer back up prevention (Back water valve check valves, sump pumps) and sewer inflow separation (gutters, yard drains, etc.)Number of Properties: 67Contractors: Coastline, National Water MainSchedule: September to November 2023Project Outreach Construction NoticesWoodstock Street Public Outreach Meeting Notice Sept. 20Water Main Replacement & Meter Pit Construction and Branford Street Project Outreach Meeting NoticeInspection Notice June