Durham Street Sewer Separation Project Area Map
Project: Work includes installation of storm drain, storm drain stub connections, sewer main lining and sewer house connection lining and manhole lining. 
Private Property work is also being offered including sewer back up prevention (Back water valve, check valves, sump pumps) and sewer inflow separation (gutters, yard drains, etc.)
Number of Properties: 24
Contractors: VMS Construction
Schedule
: July 2023 to 1st Quarter 2024 with restoration to follow
Cost: $1.9M
Work Completed:
1234 feet of main line sewer lined (complete)
21 sewer laterals/private house connections lined (complete)
1401 feet of main line storm installed (complete)
730 Feet of new water main installed (complete)
16 new water services installed (complete)
19 basement assessments completed
4 catch basins replaced

Project Outreach Construction Notices
Durham Street Phase II Update 4.1.24
Durham Street Progress Update Information Notice 2.23.24
Durham Street, Woodstock & Branford Street Public Outreach Meeting Notice
Durham Street Sewer Separation Construction Notice
Durham Street Water Main Replacement & Meter Pit Construction Notice
Durham Street Public Outreach Meeting Notice