Woodstock and Branford Sewer Separation Project Area MapProject: Work includes installation of storm drain stub connections, sewer main lining and sewer house connection lining and manhole lining. Private Property work is also being offered including sewer back up prevention (Back water valve check valves, sump pumps) and sewer inflow separation (gutters, yard drains, etc.)Number of Properties: 72Contractors: Coastline, National Water MainSchedule: September 2023 to 1st Quarter 2024Cost: $1.7MWork Completed:72 storm drain stubs installed (complete)321 feet of storm drain installed1088 feet of main line sewer lined Branford (complete)1450 feet of new water main installed Branford (complete)46 new water services installed Branford (complete)29 backwater valves installed (Branford)1058 feet of main line sewer lined Woodstock (complete)25 backwater valves installed (Woodstock)Project Outreach Construction NoticesDurham Street, Woodstock & Branford Street Public Outreach Meeting NoticeWoodstock Street Public Outreach Meeting Notice Sept. 20Water Main Replacement & Meter Pit Construction and Branford Street Project Outreach Meeting NoticeInspection Notice June