Woodstock and Branford Sewer Separation Project Area Map
Project: Work includes installation of storm drain stub connections, sewer main lining and sewer house connection lining and manhole lining. Private Property work is also being offered including sewer back up prevention (Back water valve check valves, sump pumps) and sewer inflow separation (gutters, yard drains, etc.)
Number of Properties: 72
Contractors: Coastline, National Water Main
Schedule: September 2023 to 1st Quarter 2024
Cost: $1.7M
Work Completed:
72 storm drain stubs installed (complete)
321 feet of storm drain installed

1088 feet of main line sewer lined Branford (complete)
1450 feet of new water main installed Branford (complete)
46 new water services installed Branford (complete)
29 backwater valves installed (Branford)

1058 feet of main line sewer lined Woodstock (complete)
25 backwater valves installed (Woodstock)

Project Outreach Construction Notices
Durham Street, Woodstock & Branford Street Public Outreach Meeting Notice
Woodstock Street Public Outreach Meeting Notice Sept. 20
Water Main Replacement & Meter Pit Construction and Branford Street Project Outreach Meeting Notice
Inspection Notice June