Project Area Map Project: The work consists of CCTV & Cured in place piping / Lining 22,750 linear feet of sewer main, Reconnection of 600 Active Service Laterals, 49,125 linear feet of Service Lateral Lining from the sewer main to the building or cleanout, 100 feet of Sewer Main replacement, 78 sewer main and service point repairs, 100 cleanout installations, as well as sewer manhole lining and rehabilitation in the North Meadows Area of Hartford.
Contractors: National Water MainProperties: 550Schedule: Q2 2024 – 2026Cost: $13.7MWork Completed: Mainline: all cleaning and and CCTV completed, 15% Lined Lateral CCTV and Lining: 80% Cleaning and CCTV completed